When will the paving on U.S. 17 near Shallotte be completed?

Ken Little
StarNews

The completion date for the contract is late November, said Wayne Currie, N.C. Department of Transportation Division 3 resident construction engineer.

There will be no paving on U.S. 17 until the week of July 9 due to holiday restrictions, Currie [Map this] said.

The work had been scheduled to begin in late June, but was delayed until after the Fourth of July “instead of starting and not finishing prior to the holidays,” Currie said.

“We did not want to leave a drop-off between the paved and unpaved lanes over the holiday week,” he said.

RELATED LINKS:

When will U.S. 17 repaving near Shallotte be finished, and why not repave milled roadway immediately?

Why did DOT only partially repave parts of U.S. 17 and U.S. 74/76 in northern Brunswick?

User-contributed question by:
Stacy Britt

Got a comment about this post or know more about the answer? Click here to let us know!


Bookmark and Share

X
Ask a question
X

Ask a question

If you’re looking for answers about living in coastal North Carolina, you’ve come to the right place. If we don’t have the answer to your question, we’ll find out or try to find someone who does. Hey, that’s our job! So, ask your question below and we’ll do our best to find the answer. Once we do, we’ll post it in an appropriate category.





Can we use your name to credit you by name (no e-mail or other contact information) with this question when we post an answer?
Yes
Your question:

Post a comment
X

Talk to us!

Have a comment about this post or know more about the answer? Use this form to let us know. Note that all comments are moderated and must be approved before they are posted, although you may see your own comments the first time you post them.





Your comment: