When will the bridge over Alligator Creek on the Leland causeway be open for traffic?

Julian March
StarNews

It’s unclear.

The DOT has met with the contractor to discuss the possibility of opening up the section ahead of the Nov. 15 project completion date, confirmed Brian Rick, a DOT spokesman.

“Before we can open up the additional lane and the bridge to traffic, we need to complete several items of work; the final lift of pavement, install several overhead and ground mounted signs, interim pavement markings, and a few more. This all needs to be done before we place traffic in this area,” Rick said in an email.

Rick said the contractor is putting a plan together to work toward an earlier opening of the section between the Brunswick River and the U.S. 421 exit ramp.

User-contributed question by:
Daniel G.

Got a comment about this post or know more about the answer? Click here to let us know!


Bookmark and Share

X
Ask a question
X

Ask a question

If you’re looking for answers about living in coastal North Carolina, you’ve come to the right place. If we don’t have the answer to your question, we’ll find out or try to find someone who does. Hey, that’s our job! So, ask your question below and we’ll do our best to find the answer. Once we do, we’ll post it in an appropriate category.





Can we use your name to credit you by name (no e-mail or other contact information) with this question when we post an answer?
Yes
Your question:

Post a comment
X

Talk to us!

Have a comment about this post or know more about the answer? Use this form to let us know. Note that all comments are moderated and must be approved before they are posted, although you may see your own comments the first time you post them.





Your comment: