Why are the street repairs at 41st Street and Oleander Drive taking so long?

Merton Vance
StarNews

A sewer project started in December turned out to be more complicated than anticipated, said Carey Ricks, public relations officer for the Cape Fear Public Utility Authority.

“This project included the complete replacement of a four-way manhole and associated wastewater conveyances,” she said. “Additionally, since the beginning of this project, this region has experienced periods of inclement weather that impacted construction and paving progress.

“The repairs to the wastewater system were completed on January 13th, traffic patterns reestablished, and curbing and paving work is now being coordinated and completed.”

User-contributed question by:
Tom Rivers
Tom Rivers

Got a comment about this post or know more about the answer? Click here to let us know!


Bookmark and Share

X
Ask a question
X

Ask a question

If you’re looking for answers about living in coastal North Carolina, you’ve come to the right place. If we don’t have the answer to your question, we’ll find out or try to find someone who does. Hey, that’s our job! So, ask your question below and we’ll do our best to find the answer. Once we do, we’ll post it in an appropriate category.





Can we use your name to credit you by name (no e-mail or other contact information) with this question when we post an answer?
Yes
Your question:

Post a comment
X

Talk to us!

Have a comment about this post or know more about the answer? Use this form to let us know. Note that all comments are moderated and must be approved before they are posted, although you may see your own comments the first time you post them.





Your comment: